Erb Transport
Erb Transport
Erb Transport
VCT Group worked with a local firm to secure a location to host a FIT 3.0 roof mounted contract. This was a larger rooftop project that required a dedicated communications link back to the local utility’s distribution station and included a full transfer trip and SCADA system.
Located in Baden, ON, this system is owned and operated by CED Co-operative, leasing the roof space from Erb Transport and funded by more than 700 member investors. This provides clean energy to the site, without any capital investment from Erb Transport.
Primary Equipment Installed
500kW AC / 600kW DC Ballasted rooftop system
Design Capacity
632,522 kWh / year
System Historical Performance
682,038 kWh in 2020